Audi 80/90/Coupe

since 1986-1991 of release

Repair and car operation



Audi 80/90/Coupe
+ 1.2. Car identification
+ 2. Engines, carburetors
3. Greasing system
+ 4. Cooling system
+ 5. Fuel system
+ 6. Exhaust system
+ 7. Ignition system
- 8. Transmission
   8.1.2. A fork - the main cylinder of coupling
   8.1.3. Press coupling disk
   8.1.4. Malfunctions of coupling
   + 8.2. Mechanical transmission 012
   + 8.3. Mechanical transmission 01А
   + 8.4. Automatic transmission 089
   - 8.5. Automatic transmission 087
      8.5.2. Lever and rope of the lever of gear shifting
      8.5.3. Mechanism of management of a butterfly valve
      8.5.4. Removal and transmission installation
      8.5.5. Check of the moments of gear shifting
      8.5.6. Main transfer
   8.6. Dismantling and assembly of automatic transmissions
   8.7. Block of valves
   + 8.8. Automatic transmission 097
+ 9. Suspension brackets, wheels
+ 10. Brake system
+ 11. Steering
+ 12. Body, salon
+ 13. Central air
+ 14. Electric equipment







dfe5d7b3


8.5.2. Lever and rope of the lever of gear shifting

GENERAL INFORMATION

Mechanism of the lever of gear shifting and gear shifting rope

1. 3 N of m.
2. Cover
3. Electromagnetic switch
4. Torsionny spring
5. 5 N of m.
6. Plug
7. Washer
8. Switch of the lever of gear shifting
check
the engine should be started, when the lever
switchings is in situation P or N
headlights of a backing should light up at inclusion of transfer of a backing
if is not present, turn the switch in a nest and again check its work
9. Basis
at installation put an AKD 512 001 hermetic layer between the basis and a body
10. Clip bolt
11. Boss
12. Washer
13. Coupling
14. Plug
15. Kronsheyn
16. Lock ring
17. Rope of the lever of gear shifting
with directing and the plug
grease the rope ends before installation
tighten a nut of fastening of a rope on an arm
to 15 N of m.
check, that the directing tube densely sat
move the gear shifting lever
in situation P (against the stop back)
tighten a nut of a clip of a rope to 20 N of m.

18. 23 N of m.
19. Cover
if necessary, replace
check accuracy of its installation that moisture did not get on a gear shifting rope
20. Coupling
21. Washer
22. 20 N of m.
23. The switching lever
24. Washer
25. Spring clamp
26. Plug
27. Washer
28. Compression spring
establish on the switching lever before installation of a directing pin
29. A directing pin
30. Switching lever предач
with a fork for lever locking in situation P or N
31. Casing of the lever of an adventure of transfers
it is established by P designation forward
establish after a regupirovka of the electromagnetic switch
32. Handle of the lever of gear shifting

Installation of an arm of the lever of gear shifting in relation to the gear shifting lever

PERFORMANCE ORDER
1) establish щуп And, thickness of 1.0 mm, between the lever of gear shifting and the electromagnetic switch
2) move the gear shifting lever in situation R, press the electromagnetic switch to щупу and tighten a fastening nut to 10 N of m.
3) after installation of the electromagnetic switch, establish on the center the bottom opening of a fork of the lever of gear shifting and submit tension on the switch
4) the pin of the solenoid will close a fork
5) establish a casing of the lever of gear shifting so that the lever of gear shifting was opposite to a mark N in a casing (neutral transfer);
the lever of gear shifting should pass identical distance between provisions N and D and provisions N and R
6) establish the lever A by means of a pin or a drill

In = the Pin, diameter of 4.0 mm, inserted into a casing opening
7) switch the gear shifting lever in situation in situation N
8) establish the switch so that fastening (it is specified by an arrow) was fixed on the gear shifting lever
9) tighten fastening bolts to 5 N of m.

10) remove a pin or a drill

After switch installation, check its work.